CHECKPOINT ALERT: Bridge Security
Starting Dec. 9, 2024, TSA will no longer operate Bridge Security on a regular basis. A-Bridge and Ansbacher Hall will remain open for arriving passengers and employees accessing the Airport Office Building. Departing travelers must use West Security Checkpoint or South Security Checkpoint.
Security Checkpoint Information Follow DEN on Twitter Follow DEN on InstagramTRAVEL UPDATE: Jackson Gap & 75th Ave. Detours
The existing off-ramp from inbound Peña Blvd. to Jackson Gap is closed for construction. While a temporary off-ramp is available, construction activity may cause travel impacts. Drivers on Jackson Gap will not be able to travel westbound on E 75th Ave. to the Pikes Peak shuttle lot. Detours are in place.
Peña Construction Prompts Detours for Jackson Gap and 75th Follow DEN on Twitter Follow DEN on InstagramWAYFINDING: Changes to A-Bridge/ Ansbacher Hall
A-Bridge and Ansbacher Hall will be closed for overnight construction activities from 6 p.m. to 4 a.m., Monday through Thursday nights, through the opening of the East Checkpoint in Q3 2025. During closures, all travelers must use concourse trains to journey to and from the Terminal.
Changes Coming to A-Bridge/Ansbacher Hall Follow DEN on Twitter Follow DEN on InstagramPopular Searches
News and Press
DENVER – Dec. 1, 2015 – Work to upgrade the hardware and software that operates the trains that transport passengers between the terminal and concourses is nearly complete, with the final set of early-morning scheduled maintenance shutdowns now scheduled through February.
Due to this scheduled maintenance, the trains will not be transporting passengers between the hours of 1 and 4 a.m. on Dec. 9-10, Jan. 6-8, Jan. 12-15, Jan. 26-29 and Feb. 2-5.
During the maintenance work, passengers must use the A Bridge-security checkpoint, located on Level 6, north, in Jeppesen Terminal from 9 p.m. to 4:30 a.m. during the evenings of the work because the north and south security checkpoints will be closed. The time it takes to go through the TSA security checkpoint will not be impacted because there is normally only one TSA checkpoint open between 9 p.m. and 4:30 a.m.
The majority of the flights during this timeframe depart from the A Gates so most passengers will not be impacted. However, those passengers departing on a flight from the B or C Gates between 1 and 4 a.m. will be directed through the A Bridge-security checkpoint, and will then be directed by airport personnel to bus stops for transport to the B and C Concourses. Customer service staff will be available to help guide passengers to the appropriate checkpoint and to the buses. Passengers should allow extra time to arrive at their gate.
It is possible that a few flights will arrive at the B and C Gates during this timeframe; those passengers should expect to be bused to the A Concourse for access via the pedestrian bridge to Jeppesen Terminal. Airport personnel and signage will assist with way finding. When possible, airlines may deplane passengers on the A Concourse for easier access to the pedestrian bridge leading to Jeppesen Terminal.
Airport operations will make the decision whether or not to proceed with the train shutdown each evening in case there are any significant changes in airline schedules due to weather, etc.
These are the final scheduled dates for the maintenance work. If additional dates are required, more information will be provided.
Denver International Airport is one of the busiest airports in the world. DEN is the primary economic engine for the state of Colorado, generating more than $36 billion for the region annually. For more information visit www.FlyDenver.com, check us out on YouTube and Instagram, like us on Facebook and follow us on Twitter. Sign up for DEN’s monthly newsletter Nonstop News.
###