Great Hall Completion Project

In July 2018, DEN began its Great Hall Project at the airport’s main Jeppesen Terminal. Its objective is to enhance safety and security, improve passenger flow and increase capacity. When complete, the project will deliver a safer, more efficient Great Hall that serves as a warm welcome to Denver, keeps up with passenger demand, and leaves a lasting impression for all passengers and visitors.

  • DEN was built 25 years ago for an anticipated 50 million annual passengers. In 2019, over 69 million passengers traveled through DEN
  • DEN is expecting to hit 80 million passengers by 2025 and 110 million passengers by 2040
  • When the airport opened in 1995, 60% of the passengers connected through DEN. Today, nearly 65% originate from DEN and only 35% connect and that puts much more stress on the terminal facility than ever anticipated

The Great Hall Project is following federal, state and local requirements for preventing the spread of COVID-19. The contractor is providing continual cleaning services to disinfect high-touch surfaces in common areas (meeting rooms, bathrooms, break areas, etc.), limiting the number of people in common areas and requiring face mask for workers. The contractor added trained professionals to implement  health checks that include high fever and symptom screening in accordance with City and County of Denver guidelines.

_________________________________________________________________________________________________________

UPCOMING EVENT:

Hensel Phelps’ Outreach & Project Updates for DEN Great Hall
(BHS Electrical/Low Voltage)

The Hensel Phelps Great Hall Team is hosting a virtual project update and networking event for the Electrical/Low Voltage trades for the Great Hall Project. This meeting will discuss the DEN Great Hall Project, as well as provide specific information for the Baggage Handling System Electrical/Low Voltage scopes of work. This package will have a 100% MWBE Goal.

Wednesday, August 5, 2020
1:00 PM

Each proposer must self-certify that they can meet the prequalification requirements which will include:

  • $1M Bid Bond
  • Controls experience
  • Proof of similar work in an existing facility
  • DEN experience (preferred, but not required)

Bid Due Date: Friday, August 21, 2020

Pre-Bid attendance is NOT MANDATORY but encouraged.

If you have any questions leading up to this meeting, please contact David Koob or MWBE Project Manager, Maxine Pryor. For more event details or other project inquiries, please email [email protected]

_________________________________________________________________________________________________________

 

LATEST UPDATES ON THE GREAT HALL PROJECT

Great Hall Construction Continues with Crane Work on Level 6 West  

Steelwork continues on the Great Hall Project with the addition of a second crane on Level 6. On Friday, July 17, a second crane was set-up on Level 6 west between Doors 606 and 610. Once the crane is set-up and operational, for public safety, the sidewalk, curbside check-in, passenger drop-off, and the first lane of traffic between Doors 606 and 610 will be closed.

 

 

 

 

 

 

 

 

 

 

 

The cranes on the east and west sides of Jeppesen Terminal are being used to erect structural steel that will allow for new bathrooms to be constructed on Levels 5 and 6 near the new ticketing pods and along the Level 5 baggage claim area.  The cranes will work over the sidewalk, tent canopies and on the back of the curbside check-in.

Cranes on the Exterior Level 6 as the Great Hall Project Continues

Starting Sunday, May 17 at 11 p.m., crews will install a crane on the east side of Level 6 (passenger drop-off) as part of the Great Hall Project. The crane will allow crews to begin construction on the new bathrooms on both Level 5 and 6 by installing steel.

Once the crane is installed, Doors 607-611 on the east side, Level 6 will be closed for the safety of passengers while the crane is operational. During this time, the sidewalk, curbside check-in for passenger drop-off lane and first full lane of traffic in this area will also be closed. Traffic can navigate around the closure by dropping off before or after the crane closure area. Pedestrians trying to cross on Level 6 will be directed inside, down to Level 5, through baggage claim and back up to Level 6. The crane on the east side will be in place for approximately eight weeks.

Level 6 east side crane set-up

CONTACT THE PROJECT TEAM

Hotline  (303) 342-6400
Email [email protected]

To sign up for updates or to access subscriber preferences, please enter your contact information below.